Rehabilitation of Rustaveli Street is in an active phase.
In parallel with the road paving works, the pedestrian section is being rehabilitated.
The mayor of kutaisi Giorgi Chighvaria and Deputy Mayor Yuza Ugulava inspected the works together with city council member Amiran Kopaleishvili.
According to Giorgi Chighvaria, the first layer of road surface will be laid in about 2 weeks and after that it will be possible to restore traffic.
The complete rehabilitation of the street will be completed by the end of the summer. The Regional Development Fund has allocated 3.7 million GEL for the works.
Rehabilitation of Rustaveli Street road is carried out by the ltd "Orientiri" .